Abstract— The installation of new load is a form of development of the electric power system. PHM (Pertamina Hulu Mahakam) site HCA plans to install new loads, three PCP pump units. This study aims to re-evaluate the PCP electrical system to determine whether the cable that will be used is safe and in accordance with the standards applicable in PHM, namely General specification (GS-EP-ELE-001). This research method is by simulating power flow and short circuit simulation by using ETAP 12.6 software. The results show that the N2XKBY/4C cable with a cross-sectional area of 70 mm2 and 240 mm2 is able to meet the current requirements for three PCP pump units. Voltage drop in normal or steady state conditions are PCP1 3.65%, PCP2 3.35% and PCP3 2.72%. Voltage drop in motor starting conditions are PCP1 7.22%, PCP2 6.63% and PCP3 5.42%. While the three-phase short circuit current on the bus JB-1B-P 2.32 kA, bus 1_VS 0.855 kA, bus 2_VS 1.34 kA and bus 3_VS 0.936 kA. All the results meet the PHM applicable standards. 

Intisari— Penambahan beban adalah salah satu bentuk perkembangan sistem tenaga listrik. PHM (Pertamina Hulu Mahakam) site HCA berencana melakukan penambahan beban tiga unit pompa PCP. Penelitian ini bertujuan untuk mengevaluasi ulang sistem kelistrikan PCP untuk penentuan kelayakan kabel yang akan digunakan apakah aman dan sesuai dengan standar yang berlaku di PHM yaitu General Specification (GS-EP-ELE-001). Metode penelitian yaitu dengan melakukan simulasi aliran daya dan simulasi hubung singkat menggunakan software ETAP 12.6. Hasil penelitian, kabel N2XKBY/4C dengan luas penampang 70 mm2 dan 240 mm2 mampu memenuhi kebutuhan arus untuk tiga unit PCP. Drop tegangan dalam kondisi normal PCP1 3.65%, PCP2 3.35% dan PCP3 2.72%. Drop tegangan dalam kondisi starting PCP1 7.22%, PCP2 6.63% dan PCP3 5.42%. Sedangkan arus hubung singkat tiga fasa yaitu pada bus JB-1B-P 2.32 kA, bus 1_VS 0.855 kA, bus 2_VS 1.34 kA dan bus 3_VS 0.936 kA. Seluruh hasilnya memenuhi standar yang berlaku di PHM.

Kata Kunci— simulasi aliran daya, simulasi hubung singkat, ETAP 12.6

Downloads

Download data is not yet available.

References

R. Kurniawan, S. Hani, and S. Kristiyana, “Analisa Aliran Daya Pada

Sistem Tenaga Listrik Di Pt . Kirana Megatara Menggunakan Software

Electric Transient And Analysis Program ( ETAP ) 12 . 6 62 Kurniawan ,

Analisa Aliran Daya Pada Sistem Tenaga Listrik Di PT . KIRANA

MEGATARA Menggunakan Software ,”pp. 62–69, 1990.

Mahardiananta, I. M. A., Arimbawa, P. A. R., & Santiari, D. A. S.,

Perhitungan drop tegangan sistem distribusi menggunakan metode

aliran daya. Jurnal RESISTOR (Rekayasa Sistem Komputer), 3(1), 13-

, 2020.

Badaruddin, B., Analisa Gangguan Hubung Singkat Dengan

Menggunakan Etap 12.6. 0 pada Pt X. Jurnal Teknik, 5(1), 2017.

Saputra, V. B., Analisis Gangguan Hubung Singkat Pada Sistem Tenaga

Listrik Di KSO Pertamina EP–GEO Cepu Indonesia Distrik 1 Kawengan

Menggunakan Software ETAP 12.6 (Doctoral dissertation, Universitas

Muhammadiyah Surakarta), 2016.

Alham, N. R., Utomo, R. M., Hilmansyah, H., Muslimin, M., Aditya, A.

W., & Mubarak, A., Studi Tentang Perbaikan Jatuh Tegangan Di Tiang

Ujung Jaringan Tegangan Rendah Pada Pt. Pln Up3 Area Samarinda.

Jurnal Teknik Elektro Uniba (JTE UNIBA), 6(2), 212-216, 2022.

Indonesia, S. N., Persyaratan Umum Instalasi Listrik 2011 (PUIL 2011).

Jakarta: Bsn, 2011.

Wincy, A. P., Hasjim, M., & Prabu, U. A,. Analisis Kinerja Progressive

Cavity Pump (PCP) Pada Sumur KAS 273, Lapangan Kenali Asam PT

PERTAMINA EP ASSET I JAMBI. Jurnal Ilmu Teknik, 2(2), 2014.

Omazaki, “Studi Dan Analisis Jatuh Tegangan,”[Online]. Tersedia:

https://www.omazaki.co.id/studi-dan-analisis-jatuh-tegangan/.

[Diakses 09 Juni 2022].

Pertamina Hulu Mahakam, “General Specification (Electrical GS EP

ELE 001),”Document of company, 2006.

Pertamina Hulu Mahakam, “General Specification (Electrical GS EP

ELE 001),”Document of company, 2006.

Downloads

Published

2022-10-31